All of the factory holes in the firewall were filled.

Body Modifications
The factory vents on each side of the cowl were filled in.

Body Modifications
The top cowl vent was filled in.

Body Modifications
The factory fuel filler hole was filled in.

Chassis Work
Work begins on the chassis, the frame rails are completely boxed to add rigidity to the chassis.

Chassis Work
A Heidts Mustang II cross member was added and various damaged areas on the chassis are repaired.

Chassis Work
The engine and transmission are mocked up, along with the core support.

Test fitting
The front tire placement is double checked with the body on the frame and sheetmetal mocked up.
Rear suspension
The rear suspension is set up. A Dutchman 9" ford rear end connected with a Chris Alston 4-Link kit and QA1 coilover shocks.
Mock up Continues
The new bed is fit to the truck and mini wheel tubs are added to allow for a wider rear tire.